Services Dropdown
- Communications
- Electrical Construction
- Power Line
- Renewable Energy:
- Solar
- Wind
- Substation
- Technical Services
- Transportation:
- Airports
- Bridges
- Highways


Monroe County’s new O’Rorke Bridge was designed to be a landmark structure serving Rochester’s waterfront community on Lake Ontario. The four lane double leaf Scherzer rolling-lift bascule bridge spans 243 feet across the Genesee River, replacing the Stutson Street Bridge which served the area for over 70 years. Highway approach structures from east and west total 678 feet.
Under a $5 million sub-contract from Crane-Hogan Structural Systems, O’Connell Electric provided all electrical construction and data communications work for the new bridge’s power and control systems, highway approach lighting, bridge accent lighting, security systems, and area traffic control signals.
O’Connell’s electrical work for bridge power and control systems was critical for operational reliability. The drive in each of the bridge’s bascule leaves consists of interconnected dual electric motors. Standby power for all bridge systems was supplied by an auto-start diesel generator. The control system allows semi-automatic operation of the drive system via a programmable logic computer.
O’Connell’s fiber optics work included design and installation of two-72 strand submarine cables installed under the river bed, alongside the electric, which linked bridge and highway CCTV systems, several traffic signal controls, a local water and wastewater plant, and controls for future area needs.
The computer controlled accent lighting system O’Connell installed incorporates several service levels spanning “Standard” to “Full Ornamental” for special events.

Under a $17 million grant from the FAA’s Airport Improvement Program, funding was made available for Greater Rochester International Airport (GRIA) to improve runway safety. The work involved construction of two new vehicle tunnels, addition and relocation of utilities and removal of obstructions on airport grounds to create a safety zone at the east end of runway 10/28.
On a $1.7 million subcontract from Crane-Hogan Structural Systems, O’Connell provided all electrical construction of underground conduit and cabling as well as light fixtures and controls required for the automated environmental lighting systems of the two vehicle tunnels. Fire alarm and security systems were also installed. The project spanned two years and was completed on schedule.

New York State's Department of Transportation (NYSDOT) completed an $8.5 million project to install an Intelligent Transportation System (ITS) along a four mile section of Interstate 390 near Rochester, New York. I-390 is a busy arterial route serving the area. ITS is a national program aimed at using advanced information technologies to improve transportation efficiency and safety. NYSDOT will use the system to monitor traffic conditions and issue timely information to motorists regarding accidents, congestion, and work zones.
On a $1.1 million subcontract from Crane-Hogan Structural Systems, O’Connell Electric installed and integrated Closed Circuit TV’s, Dynamic Messaging Signs, and Remote Vehicle Monitoring System Terminals for the project. The monitoring terminals are the first microwave vehicle detectors installed in Upstate New York. O'Connell performed design work to incorporate the microwave detector units into the overall system.

The Military Airport Program (MAP) uses federal funds to convert former military airports to civilian use. MAP is part of the Federal Aviation Administration’s (FAA) Airport Improvement Program (AIP) and provides a boost to civilian aviation capacity and capability. Griffiss International Airport, formerly Griffiss Air Force Base, is on the MAP project list and features a 12,000 foot long, 200 foot wide runway. Limited commercial activity makes this a niche airport for the general aviation community and a good “reliever” airport for Eastern New York State and New York City. To bring the facility up to FAA standards, this project was funded to upgrade the airport’s Navigation Aid Systems (NAVAIDS) to ensure safe and reliable operation as a civilian facility.
O’Connell was selected as prime contractor for the 6 month $4.2 million NAVAIDS upgrade project to meet FAA civilian aviation standards. Our diverse specializations and broad experience enabled us to satisfy the full Scope of Work requirements. The project demanded extensive site preparation and construction work which involved excavation, paved access roads, concrete foundations for equipment, clearing heavily wooded areas around the runway, and site restoration. O’Connell provided primary electrical service to all systems along with installing, upgrading, and testing the following NAVAIDS:
Category One Instrument Landing System (ILS)
Distance Measuring Equipment (DME)
Precision Approach Path Indicator (PAPI)
Medium Intensity Approach Lighting System with Runway Sequenced Flashers (MALSR)
Runway End Identifier Lights (REILS)
Capture Effect Glide Slope Equipment (GS)
Construction challenges included management of high ground water at the site as well as swampy areas around the facility that required proper wetlands mitigation measures. Additionally, work crews had to cope with an unusually long rainy period. The schedule was tight and required close coordination with the FAA, airport management, and tenants to maintain continuous airport operational capability. The project was a success from all technical, construction, and management aspects and all work was completed on schedule.

“Run a Red Light? Expect a Photo Finish.” That was the title of a campaign launched by the City of Rochester in advance of installing red light enforcement cameras across 50 intersections. The initiative was implemented to help decrease the number of red light running accidents as well as generate additional revenue for the City. The program required State Senate legislative approval along with the Governor’s signature to be adopted. Rochester was the first municipality in Upstate New York to implement such a program. The City partnered with Redflex Traffic Systems, Inc., an industry leader with 20 years experience building, operating, and managing digital red light and speed enforcement systems. Redflex holds contracts with over 250 cities across the U.S. as well as numerous statewide programs.
O’Connell was hired to implement the red light enforcement system throughout the City of Rochester, contracting directly with Redflex for the work at each of the 50 intersections. Our in-depth familiarity with the city municipality and understanding of New York State DOT protocols helped us secure the project, along with our competitive price. Contributing factors also included our extensive roadway, traffic signal, and street lighting experience, knowledge of Intelligent Transportation Systems, and our Closed-circuit Television, audiovisual, and data expertise. Each installation involved mounting of the Redflex detection devices to existing structures or installing proprietary pole systems to carry them. Positioning of the equipment needed to be exact to ensure optimum functionality of each install. In addition to the cameras and strobes, pavement cuts were made for installing in-pavement vehicle sensors at each intersection as well as excavation and trenching to bring in power, lay conduit, and pour foundations for the dedicated support structures.
Initial data confirms that traffic related accidents across all intersections are down.

As part of the region’s Western Gateway Initiative the City of Rochester, Monroe County, and New York State embarked on a $38 million bridge replacement project involving the heavily travelled Interstate 490/Rochester Innerloop corridor. The City of Rochester wanted a “signature bridge” to define the area’s redevelopment program for this high profile crossing of the Genesee River. To achieve this, a 433 foot steel cable arch bridge was designed to span the river rising 100 feet above the water. The bridge is one of the widest steel three-rib true arch bridges in the world (130 feet). Decorative lighting arrangements were designed to give the bridge added aesthetic appeal.
In 1972, O’Connell had provided electrical construction services on the former Troup-Howell Bridge for a major lane expansion initiative. Thirty-five years later we were back on location providing electrical construction services for lighting the new bridge. O’Connell aided field engineers in interpreting the electrical plans for the bridge’s innovative accent lighting system and worked closely with the general contractor and New York State DOT to satisfy all electrical objectives. The final results speak for themselves.

The Ogdensburg-Prescott International Bridge is a 1-1/2-mile cable suspension bridge spanning the Saint Lawrence Seaway that links the north-central border of New York State with Canada. The bridge is a vital international conduit for the transportation of persons and goods and connects much needed economic development projects for the region on either side of the border. Built in 1960, the Ogdensburg Bridge had recently been categorized as a structurally deficient surface transportation asset. Pursuant to New York State’s adopted Transportation Master Plan for 2030 the bridge was targeted for rehabilitation in order to “achieve a state of good repair” and to ensure the bridge’s longterm viability. The Ogdensburg Bridge & Port Authority partnered with the New York State Department of Transportation to implement the $48 million rehabilitation project. Work included replacement of all main span bridge decking, structural steel floor beams and stringers, raised concrete safety walks, and bridge railing systems across both approach spans and the main suspension spans.
O’Connell is no stranger to large-scale international bridge rehabilitation projects. Our portfolio includes the Thousand Islands Bridge and The Peace Bridge, which is the second busiest boarder crossing between the U.S. and Canada. Under a $3 million contract from the American Bridge Company, O’Connell was tasked with replacement and upgrade of all bridge electrical and communications infrastructure. The new two-conduit raceway system we installed spans the full 7385 foot length of the bridge, one conduit carrying wire and cable for bridge functionality, the other for future international communications. O’Connell installed newly engineered dehumidification systems into sealed vaults, where the bridge stay cables are anchored, as part of the bridge’s comprehensive corrosion protection system. We also installed all new street, bridge, and navigational lighting for the project.
The majority of electrical work and installations needed to be accomplished underneath the bridge’s surface. Demonstrating versatility and adaptability in a challenging construction environment, O’Connell researched, rented, purchased, and modified specialized equipment that enabled our technicians, and other trades, to access work areas from the topside of the bridge. With workmen suspended 100 feet, or more, over water and land during the construction period, job site safety and worker fall protection were an utmost priority. O’Connell demonstrated exceptional safety performance throughout the eighteen-month duration of the project with no reported safety incidents or injuries.
On a project of this magnitude, numerous obstacles and challenges present themselves that could not have been anticipated when bidding the work. O’Connell exhibited both the character and industry leadership qualities we are known for by managing each issue that arose and meeting all project completion schedules.

In conjunction with recent safety improvements, Greater Rochester International Airport completed an FAA runway upgrade project that involved installation of a new medium-intensity approach lighting system at the east end of runway 10/28.
On a 6 month, $900,000 contract with DME Corporation, O’Connell installed GRIA’s new approach lighting system. Our scope of work involved removal of several light towers and the existing control vault building, modifications to light towers, installation of five new light towers, new control vault building, new cabling and controls, new electrical service for the lighting system, and construction of new access roads. One challenging aspect of the project included 350 feet of directional drilling under a heavily travelled section of Interstate 390 and its off-ramps to facilitate power and controls to new light towers outside of airport property. As general contractor on the project, O’Connell provided project management as well as coordination between the FAA, GRIA operations and DME.

Rail accounts for 19% of all statewide freight flows in Alabama. The Norfolk Southern Railway is a major U.S. freight railroad company that operates 21,500 route miles of track across 22 eastern states including more than 50% of Alabama’s Class I track.
In tandem with priorities and goals outlined in the Alabama Department of Transportation’s “Alabama Rail Plan”, Norfolk Southern’s modernization and expansion initiatives targeted three vertical lift bridges in Alabama and the Norfolk Southern Lake Pontchartrain Rolling Bascule Bridge in Louisiana, the longest rail bridge in the country at 5.8 miles, for upgrade, rehabilitation, and remote control operation. These four bridges are not only critical to Norfolk Southern’s transportation grid, they are integral to the management of Alabama’s nearly 1500 mile system of navigable inland waterways, part of a network connecting 24 states.
O’Connell Electric is one of a select few electrical contractors in the country qualified to bid on this type of work. Norfolk Southern awarded our Transportation Division contracts totaling $5.9 million to rehabilitate the electrical and operating systems of the four bridges—rail and waterway—and upgrade them for remote control operation from a central site. O’Connell coordinated and supervised all machinery replacements for the bridges including new motors, brakes, span locks, and switches as well as installation of new generator platforms and numerous structural repairs.
Innovative project management and construction measures were key to O’Connell’s success and efficiency across the four remote bridge sites. A combination of well-planned prefabrication measures and deployment of custom fabrication trailers fully outfitted with tools and office communications greatly reduced lost job site time. O’Connell ingenuity was responsible for onsite rigging and hoisting systems as well as machinery and equipment replacement practices that eliminated the need for employing barges and cranes or for necessitating marine and rail traffic interruptions. In one instance we were able to place a 4000-pound 125KW generator through a machine room floor hatch more than 100 feet off the ground and rig it over the top of existing equipment within a one-hour rail traffic window.
When centralization of bridge remote operational systems was changed from Norfolk Southern’s Birmingham control center to the Decatur, Alabama, Norfolk Southern Tennessee River Bridge site, O’Connell designed and implemented all necessary modifications and additions for the site including new buildings and building amenities, service and power generation systems, and expanded electrical and communications infrastructures. Working closely with our IT subcontractor, O’Connell developed data logging systems across the four bridge network with remote access capabilities, via Norfolk Southern’s intranet, allowing instant review of all bridge operational data for diagnosing potential faults and to determine override measures in emergency situations.
Norfolk Southern’s Signals and Communications divisions contracted with O’Connell later in the project to design and construct a series of new signal and communications buildings, electrical and data wiring, and camera, intercom, and antennae systems.
All work for the four bridge project was completed on time and without disruption to marine or rail traffic. O’Connell has also worked on Norfolk Southern projects in Ohio and Chicago.